A & B Buildings Renovation

A Building Renovation

We are roughly at the halfway point in renovations. So far the roof has received a new top coating. Both buildings have received new energy efficient windows (the old windows were donated). The bathrooms in B Building have been renovated and made to work with ADA. All new lighting has been installed in the walkways. Stucco has gone up on the exterior banding. Work continues on the stair landings, stucco siding, doors, handrails, and paint. During demo, we salvaged all the cedar wood trim and the resawn boards will be reinstalled as focal walls. We continue to be on-budget and on-time to finish this renovation project by the beginning of September.

Comments are closed.